Equipment guide

Planning a central kitchen around the busiest hour

Work back from the time dough is needed at the next station. Plot overlapping batches to see when two batches would need the same trolley or receiving point.

Planning a central kitchen around the busiest hour

Start with the time dough is needed at the next station. Work backwards through portioning, transfer, discharge and mixing, using observed times from your own kitchen.

Put overlapping batches on the same timeline. If two batches need the same trolley or receiving point at once, resolve that conflict before deciding a larger mixer is necessary.